By Dovydas Kersys · Chapter 8 of 58 in Machine Commissioning.
Before you begin: Follow the machine documentation, risk assessment, site procedures and lockout/tagout requirements. Commissioning can expose personnel to electrical energy, stored pressure and unexpected motion. Never defeat a safety function merely to make a test easier. Examples and diagrams are generic and must be checked against the actual machine.
Before applying power, inspect the panel as a built assembly. Commissioning should catch wiring mistakes, loose conductors, incorrect protection, debris, unremoved transport materials and mismatched components before they become energized faults.
Why this matters during commissioning
A pre-power inspection is cheap compared with repairing a damaged drive, power supply or PLC module after a wiring error.
Commissioning procedure
- Compare installed devices with the schematic and BOM.
- Check conductor sizes, ferrules, terminal tightness, wire numbering and separation of voltage classes.
- Verify breaker/fuse ratings and adjustable settings against design.
- Inspect contactors, overloads, relays and plug-in modules for shipping damage or loose seating.
- Remove loose wire strands, cutoffs, screws and conductive debris.
- Confirm panel fans, filters, heaters and enclosure seals are complete.
Common failure patterns
- 24 VDC wired into an analog input configured for a different signal type.
- Supply and load sides reversed on a power device.
- Loose neutral or common conductor.
- Shield terminations contacting unintended terminals.
Evidence to record
- Panel inspection checklist
- Torque checks where required
- Protection settings
- Discrepancies and corrections
- Photo or redline references
FIELD RULE: Do not energize a panel that has not been physically compared with its drawings.
Appendix A. Pre-Power Checklist
Use this as a generic prompt before first electrical energization.
☐ Approved schematic and panel layout available at the machine.
☐ Main supply rating matches design.
☐ Protective earth and bonding inspected/tested.
☐ Breaker/fuse ratings and adjustable settings verified.
☐ Control transformer / power supply taps verified.
☐ 24 VDC polarity and distribution checked.
☐ No loose conductors, strands, screws or conductive debris.
☐ PLC/I/O modules seated and keyed correctly.
☐ Drive/servo motor and feedback cables verified.
☐ Neutral/commons and shield terminations checked.
☐ External feeds, UPS circuits and backfeeds identified.
☐ Panel doors, covers and barriers installed as required for the planned test.
☐ People briefed; area controlled for energization.
FIELD RULE: Add site-specific requirements and measured values. A checkbox alone is weak evidence when a numeric measurement is available.
Continue the series
- Previous chapter: Energy Control and LOTO: Commissioning Guide
- Next chapter: Protective Earth and Bonding: Commissioning Guide
- Browse all Machine Commissioning chapters
Adapted from Machine Commissioning for Maintenance and Automation Technicians, by Dovydas Kersys. © 2026 Dovydas Kersys. Featured cover image is an AI-generated editorial illustration.