By Dovydas Kersys · Chapter 21 of 58 in Machine Commissioning.

Before you begin: Follow the machine documentation, risk assessment, site procedures and lockout/tagout requirements. Commissioning can expose personnel to electrical energy, stored pressure and unexpected motion. Never defeat a safety function merely to make a test easier. Examples and diagrams are generic and must be checked against the actual machine.

Motor commissioning begins before energization. Verify nameplate data, wiring, insulation condition where required, overload/protection settings, coupling, lubrication, guarding and mechanical freedom.

Why this matters during commissioning

A drive can be configured perfectly and still fail if the motor is wired for the wrong voltage or mechanically bound.

Advertisement

Commissioning procedure

  1. Record motor nameplate voltage, current, frequency, speed and power.
  2. Confirm star/delta or other connection matches supply/drive arrangement.
  3. Check motor cable termination, PE, shield/grounding method and brake wiring if present.
  4. Verify overload or drive motor data.
  5. Check shaft/coupling condition and that the load is safe for an initial jog.

Common failure patterns

  • Wrong motor connection for available voltage.
  • Brake remains applied.
  • Motor fan direction/airflow incorrect.
  • Mechanical coupling misaligned or transport lock still installed.

Evidence to record

  • Motor nameplate data
  • Connection configuration
  • Protection settings
  • Mechanical inspection result
  • Initial jog authorization

FIELD RULE: Never auto-tune or run a motor until its nameplate and mechanical condition have been verified.